II. Review of District
Watershed Management Issues
III. Review of
Watershed Stewardship Plan Outline
·
First version of document prototype / outline focuses on
Introduction and Overview, Planning Process, Summary of Key Issues,
Methodologies, Watershed Area Description, and Watershed Unit Coarse
Level Assessment. A second
version of the outline will focus on later stages of the watershed
stewardship plans including visioning, ranking, project selection, and
implementation
IV.
Project Critical Path Issues
·
Review Schedule
·
Completion of first round of management issue
identification
·
Approval of WSP outlines through coarse-level
assessments
·
Integrate Historical Ecology project
activities with WSP project
·
Obtain updated data and information from
stakeholders and agencies
·
Select supplemental field data collection
objectives (fine-scale assessment)
·
Interviews and surveys for existing and
recommended projects – all agencies.
·
Field data collection must begin by late June
(critical decision regarding type of longitudinal profile to obtain
interns for field crew)
V. Request for Information
·
Data Request to District
·
Review / Demonstration of Data Compilation
·
Update Data Request to Stakeholder (review
upload procedures)
VI. Next Steps
·
Confirm schedule for next meeting
·
Confirm data / information delivery commitments
·
Confirm WSP outline decisions
·
Schedule supplemental field data collection
target meeting
|